Our park action plan

Care for the park now. Build an evidence-based future for living heritage and public open space.

One plan brings together the recent clean-up, safety, heritage, park design, tracks, community support, donations and events work.

Working public summary · Updated 15 November 2026

Targets and responsibilities below are proposed planning checkpoints. Committee endorsement, funding, site checks and the relevant agreements are still needed for future delivery.

Start here

The next practical steps

Make the work ready

Confirm site and area leads, released tasks, first aid, access, tools and safety arrangements before each session.

Work together

Use agreed clean-up jobs, sign-in and briefings. Record real progress with matching photos, permissions and movement records.

Build the case

Consolidate heritage evidence, scope independent studies and costs, review community views and prepare committee decisions.

Working bee dates on the website

Thursday 19 and Sunday 22 November 2026 · 10 am–3 pm both days · Queensland time

Heritage Park, 193 Rifle Range Road, Pimpama QLD 4209. Confirm access and a suitable task with the coordinator. Free food, drinks and petrol for agreed equipment are advertised. Ask before photos if you prefer not to appear.

Check details and register to help

A staged programme

From immediate care to a workable future

Proposed internal checkpoints start from 15 November 2026. They do not replace notice deadlines, extend tenure or authorise works or public opening. The pace depends on decisions, advice and resources.

  1. 15–18 November 2026

    Prepare the working bees

    Confirm coordinators, site conditions, approved task areas, supplies, ownership and evidence sheets.

  2. 19 & 22 November 2026

    Work and document

    Advertised 10 am–3 pm sessions. Undertake released jobs, record attendance and review each day's evidence.

  3. By 30 November 2026

    Set the study and funding pathway

    Review assessment scope, quotes to obtain, budget limits and current funding deadlines. Record any appointment or application decision.

  4. First 30 days

    Test the park concept

    Consolidate the inventory and heritage sources; measure a feasible footprint and route candidates; scope fire, buildings, ecology and access work.

  5. Days 31–60

    Develop a costed operating option

    Prepare a daylight-access pilot proposal, responsibilities, volunteer roster, maintenance, insurance and annual operating costs.

  6. Days 61–90

    Assemble the retention case

    Bring together evidence, independent findings available, community feedback, costs and proposed agreement terms for review.

The consolidated programme

All 13 workstreams

Each workstream has a next step, proposed lead, target and completion evidence. A prepared draft or available webpage does not establish that site work is complete or accepted.

13 of 13 workstreams shown

NowPlan prepared

Clean-up, maintenance & progress evidence

A clean-up programme and evidence templates have been prepared. Each completed site job still needs its own checked record.

Proposed lead:
Site coordinator and area leads, to confirm
Target:
Before each working bee; evidence review after each session

Next actions

  • Allocate agreed tidying, mowing and ordinary waste tasks by area; check ownership before moving an item.
  • Keep genuine before-and-after photos, item movement locations and authorised disposal records.
  • Record remaining problems and arrange qualified specialist work where needed.

Evidence of completion

A checked job record, dated photos and any required specialist evidence; Council acceptance recorded separately.

NowSite checks needed

Safety, buildings & emergency arrangements

Draft safety guidance and the safety page are prepared. On-site emergency details and technical assessments require verification.

Proposed lead:
Committee, site coordinator and competent advisers
Target:
Before volunteer work, events or public access

Next actions

  • Confirm the session lead, first aid, emergency access, briefing, PPE and weather arrangements.
  • Check barriers, workshop/vehicle separation and restricted buildings; release only suitable tasks.
  • Complete the building, fire and access assessment pathway before extending public use.
  • Scope restricted-area fencing, safety signs and printed mesh; review camera and gate arrangements before procurement.

Evidence of completion

Recorded site checks, named responsibilities and the relevant qualified assessments and approvals.

NowDates advertised

Working bees & volunteer coordination

The website advertises Thursday 19 and Sunday 22 November, 10 am–3 pm Queensland time. Members and new volunteers can register interest.

Proposed lead:
Volunteer coordinator and area leads, to confirm
Target:
19 and 22 November 2026; daily arrangements to confirm

Next actions

  • Confirm leaders, access, task boundaries, equipment and food/drink arrangements before each day.
  • Match volunteers to agreed jobs; use attendance, induction and sign-out records.
  • Record volunteer hours and publish consented progress photos and thank-yous.

Evidence of completion

Confirmed session arrangements, attendance and checked work records; photos used with permission.

NowProposal for review

Work towards a continuing SCRS role

The aim is to retain a viable restoration precinct while making more of Heritage Park available for community use. Continued tenure and a revised arrangement need written agreement.

Proposed lead:
Committee and authorised Secretary/adviser
Target:
Prepare now; external steps after recorded authorisation

Next actions

  • Keep the current compliance evidence and legal/lease dates in the private committee process.
  • Prepare a concise case covering heritage, community use, maintenance, safe operation and a workable footprint.
  • Develop questions and draft terms for an authorised discussion with Council.

Evidence of completion

An endorsed proposal and, for any agreed change, a written decision or agreement.

Next 30 daysAssessment brief prepared

Independent heritage work & rifle-range conservation

An independent assessment brief and field-evidence checklist are prepared. They are not a completed independent heritage assessment.

Proposed lead:
Heritage lead and committee; assessor to appoint
Target:
Set the brief and quote scope by 30 November; appointment subject to decision

Next actions

  • Confirm the rifle-range heritage boundary and gather genuine records, original photographs and archive references.
  • Price independent significance and retention-feasibility work, with technical services scoped separately.
  • Test conservation and interpretation of the former rifle range, machinery, steam engines and historic structures; verify surviving features before proposing reconstruction.

Evidence of completion

A sourced feature register and, after engagement, an independent report with limitations and an approval pathway.

Next 30 daysRecords to consolidate

Buildings, machinery & collection records

The next step is one consistent inventory supporting conservation, safe storage and the park proposal.

Proposed lead:
Collection custodians and Secretary
Target:
First priority register within 30 days

Next actions

  • Identify priority buildings, machinery, vehicles and display items by location, condition and custodian.
  • Confirm ownership, loan arrangements and permissions in restricted records.
  • Link each proposed retained display or building to its evidence, constraints and maintenance needs.

Evidence of completion

A reviewed priority inventory and a documented decision for every proposed retention or movement.

Next 30 daysConcept only

Living heritage park design & management

The SCRS concept combines a working heritage precinct with public open space. Facilities, footprint and access arrangements remain proposals.

Proposed lead:
Committee with technical advisers and Council agreement
Target:
Initial feasibility scope within 30 days; staged design over 90 days

Next actions

  • Test a feasible footprint for sheds, heritage displays and the former rifle range alongside walking and cycling routes.
  • Scope accessible amenities, shade, seating, gardens, BBQ areas and group/bus access.
  • Include wildlife and vegetation protection, fire constraints, gates, security, lighting, servicing and a funded operating model.
  • Test heritage garden art, large gears, workers-hut displays and optional visitor-service ideas in later stages; distinguish replicas from original heritage fabric.

Evidence of completion

A measured concept, technical feasibility advice, costed operating responsibilities and the necessary agreements.

Next 30 daysDigital guide prepared

Walking & bike tracks on phones and the website

A digital track-guide page is available. Proposed digital lines do not establish a surveyed, approved or open route.

Proposed lead:
Track coordinator and technical/site reviewers
Target:
Survey and check routes before any public opening

Next actions

  • Walk and map authorised route candidates, recording grades, surfaces, crossings and hazards.
  • Check ecological, heritage, fire and accessibility constraints; separate walking and cycling uses where required.
  • Verify phone/GPS behaviour, wayfinding and offline/emergency instructions against the actual site.

Evidence of completion

Site-verified route records, agreed access and signs, and a checked guide matching the released route.

NowWebsite tools available

Community views & show of support

The website provides a show-of-support page and a separate park comparison survey. Response totals and outcomes must come from reviewed records.

Proposed lead:
Secretary and survey administrator
Target:
Review responses weekly

Next actions

  • Invite support, alternative views and uncertainty through clear, neutral survey choices.
  • Keep support names, survey responses, donations and website views as separate measures.
  • Moderate comments privately and report the survey method, dates, counts and limitations.

Evidence of completion

A dated summary of genuine reviewed responses, with denominators and no claim to represent all residents.

Next 30 daysCosts & payment checks needed

Budget, donations & funding preparation

Donation options and a donation-suggestions form are on the website. Successful live payments, reconciliation and bank payouts require separate verification.

Proposed lead:
Treasurer and committee
Target:
Initial budget and funding check by 30 November

Next actions

  • Cost studies first, then quote measured works and recurring operating costs; record GST and contingencies.
  • Check funding opportunities, eligibility, landowner consent and closing dates before any application.
  • Review donation suggestions and payment/payout status; report income and spending only from reconciled records.

Evidence of completion

An approved budget, genuine quotes and a funding gap; verified payment/payout checks and reconciled receipts.

Next 30 daysPlanning & enquiries

Open days, vintage vehicles, group visits & new events

Recent work covers open-day support, a vintage vehicle event, NDIS/group visits, and exploratory music and woodchopping ideas. New event dates and bookings are not established by this plan.

Proposed lead:
Events coordinator and committee
Target:
Confirm each event separately before advertising a booking

Next actions

  • Confirm site suitability, dates, access, capacity, volunteers, insurance and any required permissions.
  • Prepare separate event scopes and budgets, including displays, barriers, equipment, waste and emergency arrangements.
  • Agree group support/transport and photography arrangements; keep personal participant information private.

Evidence of completion

A recorded event decision, agreed partner arrangements, budget, suitable site plan and published confirmed details.

NowPages & draft material prepared

Website, images, member updates & recognition

Recent website work includes support, surveys, clean-up, safety, donations and appreciation. Campaign images and messages need the appropriate review before use.

Proposed lead:
Secretary and authorised website/social administrators
Target:
Keep event details current; proposed weekly progress update

Next actions

  • Use realistic heritage-park concepts with prominent proposal/AI illustration labels; use genuine photos as work evidence.
  • Keep working-bee and event information consistent; respect member communication preferences.
  • Prepare reviewed member and social updates, then publish or send through the authorised process.

Evidence of completion

Accurate linked pages and approved updates, with permissions and genuine evidence behind progress claims.

OngoingProposed review cycle

Committee decisions, maintenance & progress reporting

This consolidated plan is a working public summary dated 15 November 2026. Suggested leads and target dates need committee confirmation.

Proposed lead:
Committee, Secretary and Treasurer
Target:
Weekly action review; monthly budget and maintenance review

Next actions

  • Record each task's responsible person, next step, target, evidence and decision needed in the existing private register.
  • Track prepared, approved, completed, submitted and accepted as separate states.
  • Review safety, grounds, costs, volunteer capacity and the retention case; update this public summary from checked records.

Evidence of completion

A dated action review with owners, decisions, evidence and an updated next-step list.

The basis of this plan

The City of Gold Coast records adoption of the Heritage Park Master Plan on 26 August 2025. The supplied detailed report contains a 20-year implementation plan. SCRS's living heritage concept is a separate proposal for review and discussion; it is not an approved replacement or a guarantee that SCRS can remain.

This public programme consolidates SCRS working material prepared on 14–15 November 2026. Private legal, member, ownership and detailed compliance records continue through the authorised committee process.

Heritage interpretation, public access, proposed facilities and route lines need site evidence and relevant decisions. Concept images are illustrations of possible outcomes, not records of completed works. No completion percentage or community-support total is assumed here.

Council's official master plan listing

How progress should be recorded

Prepared → approved → completed with evidence → submitted where required → accepted in writing. These are separate states. Proposed dates and suggested leads become commitments only after the relevant decision is recorded.

Help make the next step happen

Offer a few hours, share a skill or a genuine historic record, suggest a donation priority, or tell us what you would value in the park. The Secretary can match offers to the current work.

Plan page: southcoastrestorationsocietyinc.org.au/park-action-plan

For a correction or progress evidence, contact the Secretary through the website. Updates should identify the task, work date, result and supporting records.